Our Kitchen Makeover
Done by Kitchen Design Concepts
Starting January 24th 2005
Week1 Week2 Week3 Week4 Week5 Week6 Week7 Week8 Week10 Week11 Week12 Finish1 Finish2 FINAL
Day8(Monday January 31st):


Trench for Gas and Electric to the island
Day9(Tuesday):

Gas and electrical put in.
Day10(Wednesday):

hole where fireplace and brick pavers filled in

Second door bricked in.
(Click this
to see
how it used to look)
Day11(Thursday):

Insulation goes in.

HVAC starts taking shape
Day 14(Sunday):

They did some additional work on the brick to remove the half bricks at the top
It's also pretty much dry now so it's matches better.