Our Kitchen Makeover
Done by Kitchen Design Concepts
Starting January 24th 2005

Week1 Week2 Week3 Week4 Week5 Week6 Week7 Week8 Week10 Week11 Week12 Finish1  Finish2 FINAL

Day8(Monday January 31st):


Trench for Gas and Electric to the island

Day9(Tuesday):


Gas and electrical put in.

Day10(Wednesday):


hole where fireplace and brick pavers filled in


Second door bricked in. (Click this to see how it used to look)

Day11(Thursday):


Insulation goes in.


HVAC starts taking shape
 

Day 14(Sunday):


They did some additional work on the brick to remove the half bricks at the top
It's also pretty much dry now so it's matches better.
 