Our Kitchen Makeover
Done by Kitchen Design Concepts
Starting January 24th 2005
Week1 Week2 Week3 Week4 Week5 Week6 Week7 Week8 Week10 Week11 Week12 Finish1 Finish2 FINAL
Day15(Monday February 7th):

Gas and Electrical trench filled in.
Also roofing was finished today to close the hole.
Day16,17&18:
Waiting for inspection. No work was done, but
here is a
Mockup I put together of how the finished product should look (except for paint
colors)

Day19(Friday Feb 11):


Sheetrock goes in.
| < Back to Week 2 |